伊拉克Block9油田伴生气处理厂项目顺利完成火炬吊装并实现大件设备吊装里程碑

文摘   2024-09-18 22:28   阿联酋  


9月11日清晨,天气晴朗、微风徐来,在伊拉克B9油田伴生气处理厂项目(GPP)施工现场,600吨履带吊轻舒吊臂,缓缓提升、转动,顺利将最后一节火炬框架(含火炬管)吊装就位,标志着该项目完成了所有大件包括设备和模块的吊装,顺利实现又一个重要里程碑节点。

In the early morning of September 11, the weather was clear and the breeze was gentle. At the construction site of Iraq's B9 oil field associated Gas Treatment Plant project (GPP), 600 tons of crawler crane eased the boom, slowly lifted and turned, and successfully lifted the last section of torch frame (including torch tube) into place, marking the completion of the project's lifting of all large pieces, including equipment and modules. And successfully realized another important milestone node.


该油田伴生气处理厂项目设计处理能力130万标准立方英尺/天,其中酸性气火炬位于厂区西南角,为钢管框架结构,火炬正方形底部尺寸为12米 X 12米,高100.55米,是该项目乃至B9油田的最高构筑物。

The designed processing capacity of the associated gas treatment plant project is 1.3 million standard cubic feet per day. The acid gas torch is located in the southwest corner of the plant. It is a steel pipe frame structure. The square bottom of the torch is 12 meters × 12 meters and the height is 100.55 meters.

8月6日,项目开始安装框架的第一节,采取分2片吊装到基础上,然后安装连接构件、组装成框。到9月11日完成火炬第四节的吊装,在约一个月的时间完成此大型火炬的吊装和安装作业。

On August 6, the project began to install the first section of the frame, which was hoisted to the foundation in two pieces, and then installed the connecting members and assembled into the frame. By September 11, the fourth section of the torch will be completed, and the lifting and installation of the large torch will be completed in about one month.

(火炬设施第一节组装成型)

The first section of the torch facility is assembled

(火炬最后一节吊装成功后现场人员合影)

Group photo of on-site staff

GPP项目模块和大型设备多,工期紧,大件吊装一直是项目的关键工序和重点工作。寰球中东公司伊拉克B9 PMC项目部高度重视大件设备吊装作业管控,从吊装方案准备和审核、基础和设备验收、吊装设备机具检验进场、吊装前安全会议、联合检查和吊装作业监督等各环节,切实做好质量检验和安全监督,确保所有大件吊装一次成功,为项目顺利实现里程碑计划节点,提高HSE绩效,并为后续管道和电仪安装打开作业面奠定基础。

GPP project modules and large equipment, the construction period is tight, large lifting has been the key process and focus of the project. HQC Middle East Company Iraq B9 PMC project department attaches great importance to the lifting operation control of large equipment, from the lifting plan preparation and review, basic and equipment acceptance, lifting equipment and machinery inspection approach, pre-lifting safety meeting, joint inspection and lifting operation supervision and other links, to effectively do quality inspection and safety supervision, to ensure the success of all large pieces of lifting. For the project to successfully achieve milestone planning nodes, improve HSE performance, and lay the foundation for subsequent pipeline and electrical instrument installation to open the working surface.

(现场大型模块吊装作业)

On-site large module lifting operation

(项目最重的脱乙烷塔吊装)

Deethanizer Tower installation

伊拉克7~9月是一年中最热的季节,现场白天最高气温达到52摄氏度,且夏季强风天气多。寰球中东公司PMC团队员工与业主、EPC承包商等各参建方人员一起战酷暑、顶风沙,优化工序、精心组织、加班加点,顺利实现项目大件设备吊装的节点,以实际行动践行着“业主项目的成功,就是寰球的所求”的服务理念,持续打造寰球中东公司PMC特色业务品牌,凝神聚力为联合能源公司实现伊拉克B9油田上产、稳产10万桶/天的建设目标保驾护航!

July to September is the hottest season of the year in Iraq, with daytime highs of 52 degrees Celsius and strong winds in summer. HQC Middle East company PMC team staff and owners, EPC contractors and other construction party personnel together to fight the heat, top sand, optimize the process, careful organization, overtime work, successfully achieve the project of large equipment hoisting node, with practical actions to practice the "owner project success, is the world's desire" service concept, Continue to build the global Middle East company PMC characteristic business brand, focus on the United Energy company to achieve Iraq B9 oil field production, stable production of 100,000 barrels/day of the construction goal of escort!

(夕阳下的项目现场一角)

The project site at sunset